Peter Kiewit Mod Yard
Weinrich started excavation of the site June 24, 2011. The project
start included stripping the topsoil/gravel of the site east of the
large topsoil pile. Currently, WCL is in the last one quarter of removing the 62,000m3+
topsoil pile. There has been wet weather issues that has slowed the
progress of the project. As of today, there has been 10 rain days lost.